Completed Upgrade
Malt kiln upgrade: air chamber, ducts and fans — Bavaria
The old kiln used too much energy and could not hold its temperature profile — we replaced the air chamber, ducts and fans within the summer shutdown.
- Location
- Bayern, Germany
- Completed
- 2023
- Duration
- 14 weeks

-
The challenge
A fixed shutdown window of nine weeks. Welding in confined spaces. Duct routes threaded between installations that stayed in place.
-
What we did
We dismantled the old chamber and built the new galvanized plenum on an anchored steel frame. Then the ducts and dampers, the two radial fans and the heat exchangers.
We finished with air-flow measurements across the whole floor, with production already restarted.
-
The result
A stable drying profile across the whole floor. The shutdown closed on schedule.
What Raukler did
What was in our contract on this project.
- Engineering: not on this project
- Supply: not on this project
- Installation: included
- Automation: not on this project
- Commissioning: included
- Service & training: not on this project
How it went
14 weeks in total
- Dismantling the old chamber
- Steel frame and galvanized plenum
- Ducts and dampers
- Fans and heat exchangers
- Air-flow tests and handover, production running
Similar projects
View all projects
Extension
Sachsen-Anhalt, Germany · 2024
Malting plant: 4 germination boxes × 75 t with turners — Saxony-Anhalt
- Duration
- 22 weeks
- Installation
- Automation
- Commissioning
New build In progress
Dobrogea, Romania · 2025
New malting plant: 5 circular germination buildings and a silo block — Dobrogea
- Duration
- 64 weeks
- Installation
- Commissioning