In progress New build
New malting plant: 5 circular germination buildings and a silo block — Dobrogea
One of the largest new malting plants in the region: we install the circular germination buildings, the silos and the conveyors, alongside the general contractor.
- Location
- Dobrogea, Romania
- Started
- 2025
- Duration
- 64 weeks

-
The challenge
Three companies on the same site — the general contractor, the technology supplier and us — with a shared crane plan. Work at height in a windy coastal area.
-
What we did
So far: the steel structures of the five units, the cladding, the barley silos and the connecting galleries. Ahead: the malt silos, the conveyors and commissioning with the technology supplier.
-
The result
The project is in progress. We will publish the result at handover.
What Raukler did
What was in our contract on this project.
- Engineering: not on this project
- Supply: not on this project
- Installation: included
- Automation: not on this project
- Commissioning: included
- Service & training: not on this project
How it went
64 weeks in total
- Steel structures of the five units
- Cladding
- Barley and malt silos
- Conveyors and galleries
- Commissioning (planned)
Similar projects
View all projects
New build
Muntenia, Romania · 2025
Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
- Duration
- 18 weeks
- Engineering
- Installation
- Automation
- Commissioning
- Service & training
New build
Bărăgan, Romania · 2021
Grain storage base by the railway: 16 silos, 24,000 t — Bărăgan
- Duration
- 26 weeks
- Engineering
- Supply
- Installation
- Commissioning
Extension
Hajdú-Bihar, Hungary · 2023
Six 2,000 t silos with rooftop conveyors and walkways, installed through winter — eastern Hungary
- Duration
- 16 weeks
- Installation
- Commissioning