New malting plant: 5 circular germination buildings and a silo block — Dobrogea
  1. The challenge

    Three companies on the same site — the general contractor, the technology supplier and us — with a shared crane plan. Work at height in a windy coastal area.

  2. What we did

    So far: the steel structures of the five units, the cladding, the barley silos and the connecting galleries. Ahead: the malt silos, the conveyors and commissioning with the technology supplier.

  3. The result

    The project is in progress. We will publish the result at handover.

What Raukler did

What was in our contract on this project.

  • Engineering: not on this project
  • Supply: not on this project
  • Installation: included
  • Automation: not on this project
  • Commissioning: included
  • Service & training: not on this project

How it went

64 weeks in total

  1. Steel structures of the five units 1–20
  2. Cladding 16–30
  3. Barley and malt silos 24–40
  4. Conveyors and galleries 36–54
  5. Commissioning (planned) 55–64

Gallery

Similar projects

View all projects
New build

Muntenia, Romania · 2025

Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia

Duration
18 weeks
  • Engineering
  • Installation
  • Automation
  • Commissioning
  • Service & training
New build

Bărăgan, Romania · 2021

Grain storage base by the railway: 16 silos, 24,000 t — Bărăgan

Duration
26 weeks
  • Engineering
  • Supply
  • Installation
  • Commissioning
Extension

Hajdú-Bihar, Hungary · 2023

Six 2,000 t silos with rooftop conveyors and walkways, installed through winter — eastern Hungary

Duration
16 weeks
  • Installation
  • Commissioning