Completed New build
Grain storage base by the railway: 16 silos, 24,000 t — Bărăgan
An intake and dispatch base next to the railway: 24,000 t in 16 silos and wagon loading at 120 t/h.
- Location
- Bărăgan, Romania
- Completed
- 2021
- Duration
- 26 weeks

-
The challenge
A narrow plot between the railway and the road. Foundations on settling soil.
-
What we did
We laid out the silos on the plot, wrote the installation plan and erected the silos, aeration, temperature monitoring and conveyors, then the wagon loading spout.
-
The result
The first train was loaded two weeks after handover.
What Raukler did
What was in our contract on this project.
- Engineering: included
- Supply: included
- Installation: included
- Automation: not on this project
- Commissioning: included
- Service & training: not on this project
How it went
26 weeks in total
- Layout and installation design
- Flat-bottom and hopper silos
- Conveyors, aeration, temperature monitoring
- Wagon loading and commissioning
Similar projects
View all projects
New build In progress
Dobrogea, Romania · 2025
New malting plant: 5 circular germination buildings and a silo block — Dobrogea
- Duration
- 64 weeks
- Installation
- Commissioning
New build
Muntenia, Romania · 2025
Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
- Duration
- 18 weeks
- Engineering
- Installation
- Automation
- Commissioning
- Service & training
Extension
Hajdú-Bihar, Hungary · 2023
Six 2,000 t silos with rooftop conveyors and walkways, installed through winter — eastern Hungary
- Duration
- 16 weeks
- Installation
- Commissioning