Completed New build
Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
Pre-cleaning, aspiration and distribution to 12 silos, installed on the platform above them — 150 t/h from intake to cell, with no dust in the gallery.
- Location
- Muntenia, Romania
- Completed
- 2025
- Duration
- 18 weeks

-
The challenge
A narrow platform. Free-fall spouts without sharp bends. Dust below exposure limits for the operators.
-
What we did
We did the detailed design of the routes, then installed the two pre-cleaners, the cyclones, the bag filter and the spouts with a 12-way rotary distributor.
We integrated the distributor into the existing control system and trained the operators on site.
-
The result
150 t/h reached at the tests. The gallery was clean at the inspection after the first season.
What Raukler did
What was in our contract on this project.
- Engineering: included
- Supply: not on this project
- Installation: included
- Automation: included
- Commissioning: included
- Service & training: included
How it went
18 weeks in total
- Detailed design and route survey
- Pre-cleaners, cyclones and filter
- Spouts and rotary distributor
- Automation, tests and training
The gallery is the cleanest place on the site now — and that was the point.
Similar projects
View all projects
New build In progress
Dobrogea, Romania · 2025
New malting plant: 5 circular germination buildings and a silo block — Dobrogea
- Duration
- 64 weeks
- Installation
- Commissioning
New build
Bărăgan, Romania · 2021
Grain storage base by the railway: 16 silos, 24,000 t — Bărăgan
- Duration
- 26 weeks
- Engineering
- Supply
- Installation
- Commissioning
Extension
Hajdú-Bihar, Hungary · 2023
Six 2,000 t silos with rooftop conveyors and walkways, installed through winter — eastern Hungary
- Duration
- 16 weeks
- Installation
- Commissioning