Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
  1. The challenge

    A narrow platform. Free-fall spouts without sharp bends. Dust below exposure limits for the operators.

  2. What we did

    We did the detailed design of the routes, then installed the two pre-cleaners, the cyclones, the bag filter and the spouts with a 12-way rotary distributor.

    We integrated the distributor into the existing control system and trained the operators on site.

  3. The result

    150 t/h reached at the tests. The gallery was clean at the inspection after the first season.

What Raukler did

What was in our contract on this project.

  • Engineering: included
  • Supply: not on this project
  • Installation: included
  • Automation: included
  • Commissioning: included
  • Service & training: included

How it went

18 weeks in total

  1. Detailed design and route survey 1–3
  2. Pre-cleaners, cyclones and filter 4–9
  3. Spouts and rotary distributor 8–14
  4. Automation, tests and training 15–18

The gallery is the cleanest place on the site now — and that was the point.

Operations manager, grain storage

Similar projects

View all projects
New build In progress

Dobrogea, Romania · 2025

New malting plant: 5 circular germination buildings and a silo block — Dobrogea

Duration
64 weeks
  • Installation
  • Commissioning
New build

Bărăgan, Romania · 2021

Grain storage base by the railway: 16 silos, 24,000 t — Bărăgan

Duration
26 weeks
  • Engineering
  • Supply
  • Installation
  • Commissioning
Extension

Hajdú-Bihar, Hungary · 2023

Six 2,000 t silos with rooftop conveyors and walkways, installed through winter — eastern Hungary

Duration
16 weeks
  • Installation
  • Commissioning