Tower grain dryer, 40 t/h, next to the existing silos — Banat
  1. The challenge

    A fixed deadline: the harvest. The new dryer had to be connected to the existing elevator and silos without stopping the wheat intake.

  2. What we did

    We checked the foundations, erected the drying tower, the burner and the fan units, then a new 32 m elevator and the connections to the silos. Tests were run with wet maize from the first fields.

  3. The result

    The dryer started two weeks before harvest. The farm no longer pays for drying elsewhere.

What Raukler did

What was in our contract on this project.

  • Engineering: not on this project
  • Supply: included
  • Installation: included
  • Automation: not on this project
  • Commissioning: included
  • Service & training: included

How it went

10 weeks in total

  1. Foundations and anchoring 1–2
  2. Drying tower 3–6
  3. Fans and burner 5–7
  4. New elevator and connections 6–8
  5. Tests with wet maize 9–10

The first harvest with our own dryer paid for a good part of it.

Owner, arable farm

Gallery

Similar projects

View all projects
New build

Muntenia, Romania · 2025

Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia

Duration
18 weeks
  • Engineering
  • Installation
  • Automation
  • Commissioning
  • Service & training
New build In progress

Oberösterreich, Austria · 2026

Grain intake complex: steel buildings, elevator tower and a 45 m conveyor bridge — Upper Austria

Duration
30 weeks
  • Installation
  • Commissioning
Upgrade

Dobrich, Bulgaria · 2022

Upgrade: bucket elevators and pre-cleaning in a 1980s building, 35 → 60 t/h — Dobrich

Duration
8 weeks
  • Engineering
  • Installation
  • Commissioning