Completed Extension
Tower grain dryer, 40 t/h, next to the existing silos — Banat
A farm was paying others to dry its maize — we installed a 40 t/h dryer linked to its own silos, ready before the autumn harvest.
- Location
- Banat, Romania
- Completed
- 2022
- Duration
- 10 weeks

-
The challenge
A fixed deadline: the harvest. The new dryer had to be connected to the existing elevator and silos without stopping the wheat intake.
-
What we did
We checked the foundations, erected the drying tower, the burner and the fan units, then a new 32 m elevator and the connections to the silos. Tests were run with wet maize from the first fields.
-
The result
The dryer started two weeks before harvest. The farm no longer pays for drying elsewhere.
What Raukler did
What was in our contract on this project.
- Engineering: not on this project
- Supply: included
- Installation: included
- Automation: not on this project
- Commissioning: included
- Service & training: included
How it went
10 weeks in total
- Foundations and anchoring
- Drying tower
- Fans and burner
- New elevator and connections
- Tests with wet maize
The first harvest with our own dryer paid for a good part of it.
Similar projects
View all projects
New build
Muntenia, Romania · 2025
Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
- Duration
- 18 weeks
- Engineering
- Installation
- Automation
- Commissioning
- Service & training
New build In progress
Oberösterreich, Austria · 2026
Grain intake complex: steel buildings, elevator tower and a 45 m conveyor bridge — Upper Austria
- Duration
- 30 weeks
- Installation
- Commissioning
Upgrade
Dobrich, Bulgaria · 2022
Upgrade: bucket elevators and pre-cleaning in a 1980s building, 35 → 60 t/h — Dobrich
- Duration
- 8 weeks
- Engineering
- Installation
- Commissioning