Upgrade: bucket elevators and pre-cleaning in a 1980s building, 35 → 60 t/h — Dobrich
  1. The challenge

    Existing floor openings. Access only through the old doors. A shutdown of six weeks at most.

  2. What we did

    We surveyed the building and chose elevators that pass through the existing openings, brought them in by sections and installed the pre-cleaner and its connections.

  3. The result

    Almost double the throughput in the same building.

What Raukler did

What was in our contract on this project.

  • Engineering: included
  • Supply: not on this project
  • Installation: included
  • Automation: not on this project
  • Commissioning: included
  • Service & training: not on this project

How it went

8 weeks in total

  1. Building survey 1
  2. Dismantling the old elevators 2–3
  3. New elevators, by sections 3–6
  4. Pre-cleaner, connections, tests 6–8

Gallery

Similar projects

View all projects
New build

Muntenia, Romania · 2025

Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia

Duration
18 weeks
  • Engineering
  • Installation
  • Automation
  • Commissioning
  • Service & training
Extension

Banat, Romania · 2022

Tower grain dryer, 40 t/h, next to the existing silos — Banat

Duration
10 weeks
  • Supply
  • Installation
  • Commissioning
  • Service & training
New build In progress

Oberösterreich, Austria · 2026

Grain intake complex: steel buildings, elevator tower and a 45 m conveyor bridge — Upper Austria

Duration
30 weeks
  • Installation
  • Commissioning