Completed Upgrade
Upgrade: bucket elevators and pre-cleaning in a 1980s building, 35 → 60 t/h — Dobrich
New elevators and pre-cleaning inside a 1980s concrete building, with no change to the structure — 60 t/h instead of 35.
- Location
- Dobrich, Bulgaria
- Completed
- 2022
- Duration
- 8 weeks

-
The challenge
Existing floor openings. Access only through the old doors. A shutdown of six weeks at most.
-
What we did
We surveyed the building and chose elevators that pass through the existing openings, brought them in by sections and installed the pre-cleaner and its connections.
-
The result
Almost double the throughput in the same building.
What Raukler did
What was in our contract on this project.
- Engineering: included
- Supply: not on this project
- Installation: included
- Automation: not on this project
- Commissioning: included
- Service & training: not on this project
How it went
8 weeks in total
- Building survey
- Dismantling the old elevators
- New elevators, by sections
- Pre-cleaner, connections, tests
Similar projects
View all projects
New build
Muntenia, Romania · 2025
Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
- Duration
- 18 weeks
- Engineering
- Installation
- Automation
- Commissioning
- Service & training
Extension
Banat, Romania · 2022
Tower grain dryer, 40 t/h, next to the existing silos — Banat
- Duration
- 10 weeks
- Supply
- Installation
- Commissioning
- Service & training
New build In progress
Oberösterreich, Austria · 2026
Grain intake complex: steel buildings, elevator tower and a 45 m conveyor bridge — Upper Austria
- Duration
- 30 weeks
- Installation
- Commissioning