Grain intake complex: steel buildings, elevator tower and a 45 m conveyor bridge — Upper Austria
  1. The challenge

    Lifting the 45 m bridge in one go. Clay soil that turns soft after rain.

  2. What we did

    So far: the structures of both buildings, the cladding and the elevator tower. The bridge is pre-assembled on the ground in sections, ready for the lift.

  3. The result

    The project is in progress. We will publish the result at handover.

What Raukler did

What was in our contract on this project.

  • Engineering: not on this project
  • Supply: not on this project
  • Installation: included
  • Automation: not on this project
  • Commissioning: included
  • Service & training: not on this project

How it went

30 weeks in total

  1. Steel structures of both buildings 1–8
  2. Cladding and elevator tower 6–14
  3. Bridge pre-assembly and lift 12–20
  4. Elevators, conveyors, commissioning (planned) 20–30

Gallery

Similar projects

View all projects
New build

Muntenia, Romania · 2025

Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia

Duration
18 weeks
  • Engineering
  • Installation
  • Automation
  • Commissioning
  • Service & training
Extension

Banat, Romania · 2022

Tower grain dryer, 40 t/h, next to the existing silos — Banat

Duration
10 weeks
  • Supply
  • Installation
  • Commissioning
  • Service & training
Upgrade

Dobrich, Bulgaria · 2022

Upgrade: bucket elevators and pre-cleaning in a 1980s building, 35 → 60 t/h — Dobrich

Duration
8 weeks
  • Engineering
  • Installation
  • Commissioning