Completed Extension
Six 2,000 t silos with rooftop conveyors and walkways, installed through winter — eastern Hungary
Six new silos linked to the existing base by rooftop conveyors and walkways — installed through the winter months.
- Location
- Hajdú-Bihar, Hungary
- Completed
- 2023
- Duration
- 16 weeks

-
The challenge
A schedule that ran through winter. Work at height with snow and wind.
-
What we did
We erected the silos with hydraulic jacks, installed the rooftop conveyors and walkways and connected them to the existing elevator.
-
The result
Ready for harvest. Zero lost-time incidents.
What Raukler did
What was in our contract on this project.
- Engineering: not on this project
- Supply: not on this project
- Installation: included
- Automation: not on this project
- Commissioning: included
- Service & training: not on this project
How it went
16 weeks in total
- Silo erection on hydraulic jacks
- Rooftop conveyors and walkways
- Connection to the existing elevator, tests
Similar projects
View all projects
New build In progress
Dobrogea, Romania · 2025
New malting plant: 5 circular germination buildings and a silo block — Dobrogea
- Duration
- 64 weeks
- Installation
- Commissioning
New build
Muntenia, Romania · 2025
Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
- Duration
- 18 weeks
- Engineering
- Installation
- Automation
- Commissioning
- Service & training
New build
Bărăgan, Romania · 2021
Grain storage base by the railway: 16 silos, 24,000 t — Bărăgan
- Duration
- 26 weeks
- Engineering
- Supply
- Installation
- Commissioning