Six 2,000 t silos with rooftop conveyors and walkways, installed through winter — eastern Hungary
  1. The challenge

    A schedule that ran through winter. Work at height with snow and wind.

  2. What we did

    We erected the silos with hydraulic jacks, installed the rooftop conveyors and walkways and connected them to the existing elevator.

  3. The result

    Ready for harvest. Zero lost-time incidents.

What Raukler did

What was in our contract on this project.

  • Engineering: not on this project
  • Supply: not on this project
  • Installation: included
  • Automation: not on this project
  • Commissioning: included
  • Service & training: not on this project

How it went

16 weeks in total

  1. Silo erection on hydraulic jacks 1–10
  2. Rooftop conveyors and walkways 8–14
  3. Connection to the existing elevator, tests 14–16

Gallery

Similar projects

View all projects
New build In progress

Dobrogea, Romania · 2025

New malting plant: 5 circular germination buildings and a silo block — Dobrogea

Duration
64 weeks
  • Installation
  • Commissioning
New build

Muntenia, Romania · 2025

Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia

Duration
18 weeks
  • Engineering
  • Installation
  • Automation
  • Commissioning
  • Service & training
New build

Bărăgan, Romania · 2021

Grain storage base by the railway: 16 silos, 24,000 t — Bărăgan

Duration
26 weeks
  • Engineering
  • Supply
  • Installation
  • Commissioning