Completed New build
River terminal: 85 m barge-loading conveyor, 400 t/h, installed from the water — Lower Danube
Loading barges with grain straight from the terminal silos — an 85 m belt installed from the water, with the crane on a pontoon.
- Location
- Dunărea de Jos, Romania
- Completed
- 2023
- Duration
- 12 weeks

-
The challenge
A changing river level. Working windows between barge convoys. No quay along the full length.
-
What we did
From the pontoon we installed the mooring piles and the belt structure, then the belt and the telescopic loading head. Commissioning was done with the first barge.
-
The result
A 1,500 t barge loaded in under four hours.
What Raukler did
What was in our contract on this project.
- Engineering: not on this project
- Supply: not on this project
- Installation: included
- Automation: not on this project
- Commissioning: included
- Service & training: not on this project
How it went
12 weeks in total
- Pontoon, crane and mooring piles
- Belt structure
- Belt and telescopic loading head
- Commissioning with the first barge
Similar projects
View all projects
Extension
Sachsen-Anhalt, Germany · 2024
Malting plant: 4 germination boxes × 75 t with turners — Saxony-Anhalt
- Duration
- 22 weeks
- Installation
- Automation
- Commissioning
New build
Muntenia, Romania · 2025
Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia
- Duration
- 18 weeks
- Engineering
- Installation
- Automation
- Commissioning
- Service & training
New build In progress
Oberösterreich, Austria · 2026
Grain intake complex: steel buildings, elevator tower and a 45 m conveyor bridge — Upper Austria
- Duration
- 30 weeks
- Installation
- Commissioning