Malting plant: 4 germination boxes × 75 t with turners — Saxony-Anhalt
  1. The challenge

    Installation inside a building where production carried on next door. Food-grade hygiene: stainless steel, no dead zones. The perforated floors had to be level to ±2 mm over 30 m, so the turners would never touch them.

  2. What we did

    We sealed off the working area and planned the installation in zones and shifts. We installed the stainless-steel boxes, the perforated floors and the four helical turners, then the loading and unloading chain conveyors.

    Together with our partner’s automation engineer we wired the drives and ran the motion tests, then commissioned the boxes one batch at a time.

  3. The result

    First batch on spec in week 22. The old line ran without a single stop. +30 % malt capacity.

What Raukler did

What was in our contract on this project.

  • Engineering: not on this project
  • Supply: not on this project
  • Installation: included
  • Automation: included
  • Commissioning: included
  • Service & training: not on this project

How it went

22 weeks in total

  1. Mobilisation, protection of the running area 1–2
  2. Structure and stainless-steel boxes 3–10
  3. Perforated floors and turners 11–16
  4. Loading and unloading conveyors 14–18
  5. No-load tests, load tests, handover 19–22

We started the new line without losing a single batch on the old one.

Technical director of the malting plant

Similar projects

View all projects
Upgrade

Bayern, Germany · 2023

Malt kiln upgrade: air chamber, ducts and fans — Bavaria

Duration
14 weeks
  • Installation
  • Commissioning
New build In progress

Dobrogea, Romania · 2025

New malting plant: 5 circular germination buildings and a silo block — Dobrogea

Duration
64 weeks
  • Installation
  • Commissioning

Planning something similar?

Request a similar project