Completed Extension
Malting plant: 4 germination boxes × 75 t with turners — Saxony-Anhalt
A malting plant needed 30 % more capacity without stopping its running line — we installed four germination boxes with turners in 22 weeks.
- Location
- Sachsen-Anhalt, Germany
- Completed
- 2024
- Duration
- 22 weeks

-
The challenge
Installation inside a building where production carried on next door. Food-grade hygiene: stainless steel, no dead zones. The perforated floors had to be level to ±2 mm over 30 m, so the turners would never touch them.
-
What we did
We sealed off the working area and planned the installation in zones and shifts. We installed the stainless-steel boxes, the perforated floors and the four helical turners, then the loading and unloading chain conveyors.
Together with our partner’s automation engineer we wired the drives and ran the motion tests, then commissioned the boxes one batch at a time.
-
The result
First batch on spec in week 22. The old line ran without a single stop. +30 % malt capacity.
What Raukler did
What was in our contract on this project.
- Engineering: not on this project
- Supply: not on this project
- Installation: included
- Automation: included
- Commissioning: included
- Service & training: not on this project
How it went
22 weeks in total
- Mobilisation, protection of the running area
- Structure and stainless-steel boxes
- Perforated floors and turners
- Loading and unloading conveyors
- No-load tests, load tests, handover
We started the new line without losing a single batch on the old one.
Similar projects
View all projects
Upgrade
Bayern, Germany · 2023
Malt kiln upgrade: air chamber, ducts and fans — Bavaria
- Duration
- 14 weeks
- Installation
- Commissioning
New build In progress
Dobrogea, Romania · 2025
New malting plant: 5 circular germination buildings and a silo block — Dobrogea
- Duration
- 64 weeks
- Installation
- Commissioning