Grain and malting plants look simple from the outside: silos, a tower, some conveyors. The difficulty is inside — in how grain behaves, how air moves through a germination box, how an elevator is loaded so it runs for years without trouble. That is where engineering experience pays off.

Experience that shows in the details

Our engineers and site managers bring decades of combined experience in grain storage and malting. It shows in the decisions nobody sees later: the slope of a spout, the access to a drive for maintenance, the order in which a silo battery is erected so the site stays safe and on schedule.

Proven technology, installed by people who know it

We do not reinvent process technology. We work with world-class partners such as Bühler, a global leader in process technology for the food and feed industries, and integrate their equipment into complete plants. You get technology proven at large scale, and a team on site that knows how to install and connect it.

  • Process equipment from recognised partners, integrated into one design
  • Structures, piping and handling designed around that equipment
  • Installation by crews who have done it before, on similar plants
Global standards, local expertise: proven technology with project management on the ground.

Where to see it

The malting and grain handling projects below show this work in practice — from the stainless-steel germination boxes of a malthouse to the distribution gallery above a silo battery.

Related services

Projects that show it

Extension

Sachsen-Anhalt, Germany · 2024

Malting plant: 4 germination boxes × 75 t with turners — Saxony-Anhalt

Duration
22 weeks
  • Installation
  • Automation
  • Commissioning
New build

Muntenia, Romania · 2025

Pre-cleaning tower and distribution gallery above 12 silos, 150 t/h — Muntenia

Duration
18 weeks
  • Engineering
  • Installation
  • Automation
  • Commissioning
  • Service & training
Upgrade

Dobrich, Bulgaria · 2022

Upgrade: bucket elevators and pre-cleaning in a 1980s building, 35 → 60 t/h — Dobrich

Duration
8 weeks
  • Engineering
  • Installation
  • Commissioning