A running malthouse cannot afford weeks of downtime. An extension — new germination boxes, a modernised kiln, more storage — has to be built while production continues. It can be done if the work is planned in stages from the start.

What staging means

  • The new section is built alongside, as separate as possible from the one that produces: foundations, structure, equipment.
  • The connections are prepared in advance: grain, air, water and power routes to the existing section are designed so that connecting takes little time.
  • The switch-over is scheduled with the production team, in the windows where a partial stop matters least.

What is checked first

Before any drawing, we look at what exists: the structure of the buildings, the capacity of the air and power systems, the grain handling routes and the space available. This shows whether the extension fits in the existing building or needs a new hall, designed around the process.

The shortest stop is the one planned from the first drawing.

Modernisation or extension

Sometimes you do not need more capacity but the same capacity, better: a kiln with new fans and ducts, boxes with new turners. These are also done in stages, section by section.

How we start

Send us your current and target capacity, the malt types and what you want to change. We visit the site and propose the stages. See what we deliver on the malting lines page.

Related services

Projects that show it

Extension

Sachsen-Anhalt, Germany · 2024

Malting plant: 4 germination boxes × 75 t with turners — Saxony-Anhalt

Duration
22 weeks
  • Installation
  • Automation
  • Commissioning
Upgrade

Bayern, Germany · 2023

Malt kiln upgrade: air chamber, ducts and fans — Bavaria

Duration
14 weeks
  • Installation
  • Commissioning